The Ritz-Carlton, Paradise Valley was supposed to open in summer 2020. The target then moved to the first quarter of 2021, and after that to fall 2022, PHOENIX magazine reported in April 2021. In 2017 the Paradise Valley Independent described an even earlier goal, a public debut in late 2018.
The newest date in the project's paperwork is April 30, 2027. It is the latest day by which a sale of the hotel would close under a schedule the developer's bankruptcy lawyers proposed in October. The resort on Scottsdale Road is no longer waiting on a construction crew. It is waiting on a buyer, and the dates that will decide what Paradise Valley gets on that land are court dates.
The October filing changed what kind of case this is
Five Star Development and its affiliates filed for Chapter 11 on November 4, 2025, in the U.S. Bankruptcy Court for the Southern District of Texas. At the time, the company described the filing as a "court-supervised path toward completing" the resort and The Palmeraie, a 122-acre resort, residential and retail project. In that announcement, the company said it intended to keep control of the project and work toward "a full construction restart."
Eleven months later the direction is different. On October 14, 2026, the entities behind the resort, called the Ritz Project Debtors in the filings, filed a disclosure statement for a plan they describe in plain terms:
"The Plan is a liquidating plan under which all of the Ritz Project Debtors' assets will be transferred to, and vest in, the Plan Trust on the Effective Date."
Lance Miller, the chief restructuring officer, would serve as the first trustee of that Plan Trust. The trust would hold the undeveloped real estate, the unsold villas, and whatever money comes from selling the hotel and its furniture, fixtures and equipment. Under the plan, the debtors would market and sell the hotel after the court confirms the plan. The Phoenix Business Journal summed up the plan's scope the same way: the incomplete hotel, the unsold villas, and land set aside for a luxury shopping center.
The 2025 announcement described a developer finishing its own resort. The 2026 plan describes a set of assets being turned into cash for the people owed money. Madison Realty Capital, the senior lender, is paid first from villa sale proceeds, and its secured claims receive the plan's A trust interests, which come ahead of the other classes in the payout order.
Ten bids so far, and still no buyer named
The search for a buyer started months before the plan was filed. A motion docketed on October 19, 2026 says the marketing process for the hotel began April 15, 2026, with JLL as the debtors' real estate adviser. Since then JLL has contacted 137 potential investors and received bids from ten of them. According to the filing, several of those investors have said they want to be the stalking horse bidder, the opening offer that sets the minimum for any auction. The motion does not name any of them.
A sale does not mean the Ritz-Carlton name leaves the property. The October disclosure statement says that once the hotel is running it will be operated by The Ritz-Carlton Hotel Company, LLC, a Marriott International subsidiary. The plan also treats the Ritz-Carlton contracts as assumed, so the brand agreements stay in place. Whoever buys the building would likely be buying a Ritz-Carlton project. What changes is who pays to finish it.
The calendar from here to spring
Some of the dates below are already set in the October 14 disclosure statement. The rest come from the October 19 motion, which asks the court to approve a sale schedule. Until the judge rules, those later dates are a proposal. All times are prevailing Central Time.
| Date | What happens | Status |
|---|---|---|
| December 4, 2026 | Deadline to object to the plan | Set in disclosure statement |
| December 7, 2026, 1 p.m. | Ballots due | Set in disclosure statement |
| December 15, 2026, 1 p.m. | Combined confirmation hearing | Scheduled; the court may adjourn it |
| January 15, 2027 | Stalking horse notice deadline; election on undeveloped real estate | Proposed |
| February 23, 2027 | Qualified bids due | Proposed |
| February 26, 2027, 10 a.m. | Auction, if one is needed | Proposed |
| Week of March 15, 2027 | Sale hearing | Proposed, subject to court availability |
| April 30, 2027 | Latest date for the sale to close | Proposed; can be extended |
On the day this post goes live, the December 15 hearing is about five weeks away. The motion says the plan has not yet been confirmed, and it gives December 15 as the hearing date. The April 30 closing date is less firm than it looks. A footnote in the motion says the sale deadline can be extended twice, by six months each time, if the debtors file a notice with the court. With both extensions, the closing could move to spring 2028.
January 15 is the date that matters most for The Palmeraie
For residents who were looking forward to the shops and restaurants more than the hotel rooms, the most important line in the schedule is easy to miss. By January 15, 2027, the debtors are to file a notice saying whether the undeveloped real estate will be included in the hotel sale or left out of it. That notice will show whether one buyer is expected to end up with the resort and the surrounding land together, or whether the land is handled on its own track inside the trust.
The retail piece also reads differently than it did a year ago. In November 2025, a sworn filing from Five Star described the hotel's restaurants as "globally recognized restaurants, including Mott 32 and Carbone." It said The Palmeraie was a fully entitled 29-acre district where "multiple global luxury brands have executed leases or LOIs." The October 2026 disclosure statement repeats most of that description almost word for word. The restaurant line, however, now stops at "globally recognized restaurants" with no names. The Palmeraie is still described as planned, at roughly 160,000 square feet of "world-class luxury retail, dining, and experiential offerings," and the sentence about signed leases is gone.
Put the two filings side by side and the retail district looks less like a near-term opening. It reads more like an approved plan that will be passed to whoever controls the land next.
The part of the project that already has neighbors
People already live at this site, which is easy to forget when driving past the unfinished hotel. The November 2025 filing said 44 villas had sold, with more ready to close over the following months. By October 2026, the disclosure statement described "the vast majority" of the 80 Ritz-Carlton-branded villas as occupied. It said several of the 32 estate homes were occupied, under construction or under contract.
The residences kept moving while the hotel stopped. The same 2025 filing said the overall project had been "substantially or entirely stalled since early 2025," when funding from Madison slowed and then stopped. It also said substantially all infrastructure was complete. When the case was filed, Five Star said it would keep full-service amenities running for homeowners and residents without interruption.
The Town's involvement goes back to early 2016. According to the Paradise Valley Independent, the Town Council approved the special use permit by a 4–3 vote that year. At the time, PHOENIX magazine described the hotel as a 215-room resort on 20 acres west of Scottsdale Road, along the north side of Lincoln Avenue, within a planned $2 billion community. The plans still list the same pieces: a 16,000-square-foot spa, more than 80,000 square feet of outdoor event space, and a 400-foot pool. Ten years after approval, those features belong to a sale process rather than a construction schedule.
Court documents, the claims process and new filings are posted on the Stretto case site. Nothing here is legal or financial advice. Anyone who holds a claim, owns a residence in the project, or has a contract tied to it should talk with their own attorney about what the filings mean for them.
If you own a home near Scottsdale Road and Lincoln Avenue and want to know how a change in ownership at the resort could figure into your own plans, Fine Homes Group is following this case closely. We'd be glad to set up a white-glove consultation, or prepare a complimentary home valuation that accounts for how this corner may develop.